Re-sealing on Rancho Santa Fe roads delayed until July
The road re-sealing schedule for several Rancho Santa Fe roads has been pushed back once again. San Diego County’s department of public works construction inspection staff has been working to resolve testing requirements/procedures prior to the resurfacing and this has caused some delays in the schedule. Below is the tentative updated timeline for the first portion of resealing:
Street Start date duration (days)
Las Planideras July 19 3
Rambla de las Flores July 23 3
Via de Fortuna July 24 4
Los Morros July 26 3
Lago Lindo July 30 3
Mimulus July 31 3